If you want to know how to build a shed base that stays flat, dry and solid, the short answer is: pick the right base type, dig out to firm ground, compact a proper sub-base, then build the surface dead level. Concrete suits heavy sheds and workshops, paving slabs suit most garden sheds, and a gravel grid or timber frame suits lighter sheds and awkward ground. Most bases are a one or two weekend job with the right kit.

In this guide
This guide walks through each option, how to size and mark out, how much to dig, which machines are worth hiring, and the mistakes that cause sheds to rot, rock or crack. Everything here is general information for garden and small-site work in Devon, Cornwall, Somerset and Dorset, where wet winters and clay or stony ground make the sub-base more important than people expect.
Which shed base: concrete, paving slabs, gravel grid or timber frame
The base spreads the shed’s load so nothing sinks and keeps the timber floor off wet ground. The right type depends on contents, size and ground.
| Base type | Best for | Typical build | Main pros | Main cons |
|---|---|---|---|---|
| Concrete slab | Large sheds, workshops, garden offices, ride-on mower or motorbike storage | 100mm Type 1 sub-base, membrane, 75 to 100mm concrete in timber formwork | Strongest, longest-lasting, takes point loads | Most work, needs curing time, hardest to remove later |
| Paving slabs | Standard garden sheds and summerhouses | Compacted Type 1, sand and cement bed, 600 x 600mm slabs | Clean finish, can be lifted and reused | Needs careful levelling, can rock if the bed is poor |
| Gravel grid | Light to medium sheds, greenhouses, sites with drainage problems | Compacted sub-base, membrane, plastic grid filled with gravel | Free-draining, quick, no wet trades | Less suited to heavy point loads |
| Timber frame | Sloping gardens, light sheds, places where you cannot dig much | Treated bearers on pads, slabs or ground screws | Copes with slopes, raises the floor for airflow | Timber needs to be properly treated and kept off the soil |
If the shed will hold a workbench, heavy tools or anything you roll in, go for concrete or slabs. On ground that holds water, a gravel grid on a good sub-base often outperforms a poorly laid slab base.
Sizing the base and marking it out
Measure the shed floor, not the roof. Roof overhangs are often 100mm or more wider than the floor frame, and people regularly build bases to the roof size by mistake. Check the manufacturer’s instructions too, because some ask for a base slightly larger than the floor and some ask for it flush.
A base a little larger than the floor, typically 50 to 100mm overall, gives you some tolerance and a clean edge. Do not go much bigger. A wide lip of concrete or slab outside the walls collects rainwater and splashes it back onto the bottom of the cladding, which is where sheds rot first.
Marking out square
- Knock in a peg at one corner and run a string line along the first side.
- Use the 3-4-5 method to set a right angle: measure 3m along one line, 4m along the other, and adjust until the diagonal is exactly 5m. Scale it down to 0.6, 0.8 and 1.0m on small bases.
- Peg the remaining corners and set strings slightly outside the dig line so they don’t get in the way.
- Check both diagonals. If they match, the rectangle is square.
- Spray-mark the outline on the ground before you lift the strings.
Planning permission and building regulations for sheds
Before you work out how to build a shed base, check the shed itself is allowed. In England, most garden sheds are outbuildings that fall under householder permitted development, so they do not need planning permission if they meet the limits. The Planning Portal outbuildings guide sets these out. In summary, as general information:
- The outbuilding must be single storey and not forward of the principal elevation of the original house.
- Maximum height is 4m with a dual-pitched roof or 3m for other roofs, with eaves no higher than 2.5m.
- Within 2m of a boundary, the whole building must be no higher than 2.5m.
- Outbuildings, extensions and other structures together must not cover more than half of the land around the original house.
- Raised platforms or decking must be no more than 300mm high.
- Different rules apply on designated land, such as national parks, National Landscapes (AONBs), conservation areas and World Heritage Sites, and within the grounds of a listed building.
That last point matters in the South West. A lot of Devon and Cornwall sits inside Dartmoor or Exmoor National Park, a National Landscape or a conservation area. Permitted development rights can also be removed by an Article 4 Direction or a condition on the original planning consent, so check with your local planning authority if you are unsure. Rules differ in Wales and elsewhere in the UK.
Building regulations may not apply to a small detached shed used for storage, but they can apply depending on size, use and location, for example if it will be a sleeping space or sits close to the house. Check the current guidance before you start a larger garden building.
How to build a shed base: the groundwork stages
Whatever surface you finish with, these first stages are the same, and they decide how well the base performs.
Step 1: check for services
Gardens hide drains, water pipes, outside lighting cables and sometimes gas or electricity supplies to outbuildings. Find manhole covers and stopcocks, ask the previous owner if you can, and hand dig carefully near any suspected run. For deeper work, read the HSE guidance on working near underground services.
Step 2: strip and dig out
Remove turf and topsoil until you reach firm, undisturbed subsoil. For a slab or concrete base, a typical dig is around 150 to 200mm below finished ground level, enough for about 100mm of compacted Type 1 plus the slab or concrete. On soft clay or made ground you may need to go deeper to find something solid. Never build on topsoil; it is full of organic matter and will settle.
Step 3: lay and compact the sub-base
Spread MOT Type 1 crushed stone in layers no thicker than about 75 to 100mm and compact each layer with a plate compactor. Several passes in different directions, with the stone slightly damp, gives a tight, firm layer that doesn’t move underfoot. Rake it to roughly the right level before the final passes.
Step 4: set levels
Use pegs and a long spirit level, or a laser level if you have one, to set the finished height. For a shed base, aim for level in both directions. A shed floor frame that sits on a level base keeps the doors square and stops windows twisting.
Building a concrete shed base
Concrete is the strongest option and the one most people mean when they ask how to build a shed base for a workshop. It takes more preparation but the method is simple.
Formwork
Build a frame from straight timber boards set on edge, for example 100 x 25mm or 150 x 25mm, held with stout pegs on the outside every 600 to 900mm. The top of the formwork is your finished level, so set it carefully and check the diagonals again. Screw the corners rather than nailing so you can strip it easily.
Membrane
Lay a polythene damp-proof membrane over the compacted sub-base, with a thin layer of sand blinding first if the stone is sharp. Lap joints by at least 150mm and run the sheet up the inside of the formwork. The membrane stops moisture wicking up through the slab and keeps the concrete from losing water into the stone while it cures.
Concrete thickness and mix
For a standard garden shed, 75mm of concrete over a good sub-base is often enough. For a large shed, workshop or anything heavy, 100mm is the safer choice. A common general-purpose mix for bases is around 1 part cement to 5 parts all-in ballast, mixed with just enough water to make it workable. Too wet and it shrinks and cracks; too dry and it won’t compact.
Working out quantities
Multiply length by width by depth in metres. A 3m x 2.4m base at 100mm thick is 3 x 2.4 x 0.1 = 0.72 cubic metres. Add about 10 percent for waste and uneven ground, so plan for roughly 0.8 cubic metres. Bag-mixing that by hand is a heavy day, which is why most people hire a mixer.
Pouring and finishing
- Start at the far end and fill the formwork slightly proud.
- Tamp the concrete with a straight board across the formwork, using a chopping motion to knock out air, then a sawing motion to strike it level.
- Work towards the near end in sections so each batch knits into the last.
- Fill any low spots and tamp again.
- Finish with a float for a smooth surface, or leave the tamped finish for a little grip.
Curing
Cover the slab with polythene or damp hessian to stop it drying too fast in sun or wind, and protect it from frost and heavy rain for the first day or two. You can usually walk on it carefully after a day or two and strip the formwork after a few days. Most people wait about a week before building a shed on it. Concrete continues to gain strength for around four weeks, so don’t drive heavy loads onto it early.
Building a paving slab shed base
- Prepare and compact the Type 1 sub-base as above, around 100mm thick.
- Set string lines at finished level along two sides.
- Mix a semi-dry bed of sharp sand and cement, roughly 6 parts sand to 1 part cement, or a mortar bed for heavier use.
- Lay each 600 x 600mm slab on a full bed, not five dabs, so there are no voids for it to rock on.
- Tap down with a rubber mallet and check level across each slab and across neighbouring slabs.
- Keep joints tight and consistent; for a shed base they can be butted or left at a few millimetres and pointed.
- Leave the bed to set before you put any weight on the slabs.
A full bed is the step that makes the difference. Slabs on spot dabs can look fine on day one, then crack under a loaded shelf or rock when the ground moves in a wet winter.
How to build a shed base with a gravel grid or timber frame
Gravel grid
Plastic grid bases are quick and drain freely, which suits gardens that hold water. Dig out, lay and compact a sub-base, lay a weed membrane, clip the grid panels together on top, then fill the cells with clean angular gravel, for example 10 to 20mm. The sub-base still matters: a grid laid straight on soft soil will settle unevenly. Check the grid maker’s load guidance for heavier sheds.
Timber frame
A frame of pressure-treated bearers, set on concrete pads, slabs or ground screws, works well on slopes because you can pack or adjust each support to level. Keep timber clear of the soil, leave a gap for air underneath, and use timber rated for ground contact where it is close to the ground. Use a lightweight membrane or gravel under the frame to keep weeds down.
The kit list: what to hire for a weekend shed base
You can build a small base by hand, but if you are planning how to build a shed base in a single weekend, a few hired machines turn a week of hard labour into two days. Here is a typical kit list.
| Job | Hire option | Why it helps |
|---|---|---|
| Digging out | Sunward SWE 08B micro excavator | A 0.8t machine small enough for most garden access, digs out a base in an hour or two |
| Moving spoil and stone | Hyundai 500kg tracked dumper or HG 1000 electric wheeled dumper | Saves dozens of barrow trips through the side gate |
| Compacting the sub-base | Weber MT CF 1-III Hd or CF 2-II Hd plate compactor | Compacts Type 1 properly so the base doesn’t settle |
| Mixing concrete or mortar | Altrad Belle Mini Mix 150 or a Baron forced action mixer | Consistent batches without bag-mixing on a board |
| Washing down | Brendon 35KPE mobile power washer | Cleans tools, mixer and paths before kit goes back |
You can find the digger, plates, dumpers and Baron mixer on our construction equipment page, and the Mini Mix 150 on our hand tools and mixers page. For more on the micro digger, read our Sunward SWE 08B guide.
Which mixer
The Altrad Belle Mini Mix 150 is electric, compact and easy to wheel round to the back garden. Its 150 litre drum mixes less than 150 litres of wet concrete per batch, so a base of around 0.8 cubic metres means a lot of batches and a full day with two people. For bigger bases or stiffer mixes, ask us about the Baron forced action mixer. For very large slabs, ready-mixed concrete may be quicker, provided the lorry or a barrow route can reach the garden.
A worked example: a 3m x 2.4m workshop shed on a sloping Devon garden
To show how the stages fit together, here is an illustrative plan for a typical job: a 10ft x 8ft workshop shed at the bottom of a gently sloping garden with clay subsoil and a 900mm side gate.
- Friday morning: micro digger, tracked dumper and plate compactor delivered. Mark out a 3.05m x 2.45m base, check diagonals.
- Friday: strip turf and dig to firm clay. On the high side the dig is deeper, on the low side shallower, so the finished slab ends up level. Dumper takes spoil to a pile for re-use in borders.
- Saturday morning: Type 1 delivered to the front, dumpered to the back, laid in two layers and compacted. Formwork set at finished level.
- Saturday afternoon: membrane down, mixer set up next to the base, 100mm concrete poured, tamped and covered.
- Monday: machines collected. Formwork stripped later in the week.
- The following weekend: shed erected on bearers or directly on the slab, depending on the manufacturer’s instructions.
On a slope, brace the low side of the formwork well from the outside, because wet concrete pushes hard on the boards. On a steep slope, a timber frame may be easier than a deep slab.
South West ground and weather: what to allow for
Much of Devon and Cornwall has heavy clay, shillet or granite-derived soils that drain slowly, and a long wet season. That shapes how you build.
- Clay: holds water and moves as it wets and dries. Dig to firm subsoil, use a full sub-base, and keep gutter water away from the base.
- Stony or shillet ground: often firm, but expect to break out stones. A micro digger saves a lot of effort here.
- Made ground: older gardens may contain rubble or old foundations. Dig until you reach consistent ground.
- Rain: don’t pour concrete onto a waterlogged sub-base, and cover fresh concrete if heavy rain is forecast.
- Frost: avoid pouring when frost is likely in the first couple of nights unless you can insulate the slab.
Common mistakes when building a shed base
- Base far too big: rainwater pools on the lip and rots the cladding.
- Spot-bedding slabs: voids underneath cause rocking and cracking.
- Concrete too wet: extra water weakens it and causes shrinkage cracks.
- No membrane: damp wicks up into the shed floor.
- Timber touching soil: untreated or poorly treated bearers rot quickly.
Hiring the kit: booking, delivery and safety
We don’t take online bookings. WhatsApp or call us with the machines you want, your postcode, the dates and access details such as gate width and any steps. Daily and weekly hire both work well for shed bases; weekly is often more relaxed if the weather turns. We deliver from our depot near Okehampton across Devon and Cornwall, often the same day, and also cover Somerset and Dorset.
Hire is self-drive, so whoever uses the machines must be competent to operate them. We’ll walk you through the controls on delivery. Plate compactors cause vibration and noise, so wear hearing protection and gloves, and take regular breaks. Cement burns skin, so wear gloves and eye protection when mixing. Insurance is not automatically included with hire; we can point you to our partner insurance4plant for plant hire cover.
Frequently asked questions
How thick should a concrete shed base be?
For most garden sheds, about 75mm of concrete on 75 to 100mm of compacted Type 1 is common. For workshops, large sheds or heavy contents, go to 100mm of concrete. Soft ground may need a deeper sub-base.
Can I put a shed straight onto gravel?
Loose gravel on soil tends to shift and settle. A gravel base works when it sits on a compacted sub-base and is held in a grid, which keeps the surface level and free-draining.
Should a shed base be level or have a fall?
A shed base should be level so the frame and doors stay square. Manage water by keeping the base edge close to the shed footprint and directing gutters and surface water away.
Do I need a digger to build a shed base?
Not for a small base on easy ground. For larger bases, clay, stony ground or a long barrow run, a micro digger and small dumper save hours and a lot of effort.
Is a paving slab base strong enough for a shed?
Yes, for most standard garden sheds, provided the slabs sit on a full bed over compacted Type 1. For very heavy contents or vehicles, concrete is the better choice.